Timber frame garden room/office Dawlish: week 2 update

Construction of timber frame garden room/office Dawlish, Devon: end of week 2 update

Work continues on our project in Dawlish, the partial demolition of an outbuilding and construction of a timber frame garden room/office. During week 1 the roof and frontage were demolished and foundations were dug out and laid. At the beginning of week 2 the blockwork was started and by Wednesday we were ready to begin erecting the timber frame. At the end of play on Friday the structure was really starting to take place.